Lane Shift: Marigold Avenue at San Lorenzo Road 4/10-5/25
Published on April 06, 2026
Marigold Avenue
Safety Improvements and Roundabouts
Peabody Road to San Lorenzo Road
Traffic Advisory: Lane Shift on Marigold Avenue at San Lorenzo Road
Please be advised of an upcoming lane shift on Marigold Avenue at the San Lorenzo Road intersection for roundabout construction. The shift will begin on Friday, April 10 between 3 and 4 a.m. and remain in place through Tuesday, May 26.
Drivers on both eastbound and westbound Marigold Avenue approaching San Lorenzo Road will shift onto newly constructed temporary lanes. Temporary barrier walls will be in place along the outside lanes to prevent vehicles from entering the work zone.
San Lorenzo Road between Valnera Court and Delano Court will remain closed through May 26. Detours are in place to direct traffic.
Sidewalks are closed at this intersection. Pedestrians and bicyclists should follow posted detour signage and avoid the work zone.
Construction schedules may change due to weather or unforeseen conditions.
For more information, call 407-349-4004 or email MarigoldAvenue@qcausa.com. To stay up to date on Osceola County lane and road closures, please visit osceolafl.co/TMAS.